Soakwell Requirements: City of Cockburn
The City of Cockburn’s residential soakwell requirements call for 12.5 litres of storage per square metre of roof and paving that drains to the system. The City requires stormwater to stay on the lot, in soakwells or another approved system. For the distance from house footings, start with the clearance in your approval or engineering design.
Published Updated
WA Soakwells
Sized to your council’s rule
We work out the soakwell volume your roof, paving and council need before we price, so the system copes with a storm.
No call-out fee
City of Cockburn Soakwell Sizing Rule
For each catchment, divide the area in square metres by 80 to get the required storage in cubic metres. Count the roof and hard paving that drain to that part of the system. The City of Cockburn’s residential drainage guide sizes storage for a “1 in 20 year storm of 5 minutes duration”.
Say a house has 180 m² of roof and 40 m² of paving feeding one linked system. Divide 220 by 80 to get 2.75 m³, or 2,750 litres. If each soakwell you choose holds 1.3 m³, two hold 2.6 m³ and fall short. Round up to three. The guide requires pipes linking soakwells in the same catchment to be at least 100 mm in diameter.
Placement and Distances
Cockburn’s residential drainage guide gives no fixed minimum distance from house footings. Use any clearance specified in your approval or engineering design. If the drawings give no clearance, mark the soakwell depth and its distance from the nearest footing and boundary. Show those measurements to your building surveyor to confirm the setback before you dig.
The WA stormwater management manual gives soil-based design guidance for infiltration systems. Its recommended minimum distances from footings include 1 m in sand, 2 m in sandy clay and 5 m in heavy clay. The clearance protects footings from changes in soil moisture.
Approvals and Inspections
If your project needs development approval, Cockburn’s planning application checklist asks how you will manage stormwater and requests plans and calculations. A planning approval can also require you to submit drainage details with the building permit application or have the design certified by an engineer.
For inspections, use the requirements on your building permit. If it calls for a drainage inspection before backfilling, arrange it while the soakwells and pipes are visible. The City’s building permit guidance requires you to attach the certificates for applicable inspections and tests to the Notice of Completion.
Local Soil and Exceptions
Cockburn’s sizing formula assumes the lot sits above the surrounding road and has a path for water to flow across the surface in a larger storm. If either condition is missing, the guide says the City will flag the flood risk on the building application.
Clay drains more slowly than sand, and shallow groundwater can limit how much water the ground can absorb. The Muriel Court water management strategy, for example, identifies shallow groundwater as a design issue for that development area. Check the lot’s approval conditions and use the Perth Groundwater Map for an initial estimate of groundwater depth. If the soil drains slowly or groundwater is close to the proposed soakwell base, have a drainage designer check the soil and seasonal water level before settling on a layout.