The City of Swan’s soakwell sizing guide uses 12.2 litres of storage per square metre of roof for a single home. That figure assumes clean sand. Before sizing anything, check whether the City lists your lot for on-site soakwells or for a connection to its road drainage system.

Published Updated

WA Soakwells

Sized to your council’s rule

We work out the soakwell volume your roof, paving and council need before we price, so the system copes with a storm.

Get a free quote

No call-out fee

WA Soakwells

Sized to your council’s rule

We work out the soakwell volume your roof, paving and council need before we price, so the system copes with a storm.

Get a free quote

No call-out fee

City of Swan Soakwell Sizing Rule

For a single home draining to on-site soakwells, multiply the roof area in square metres by 0.0122 to get the storage volume in cubic metres. The City’s Soakwell Capacity table bases that rate on a 1-in-5-year storm. It gives a separate rate of 15.9 litres per square metre of impervious area for industrial, commercial and high-density residential development.

These are selected sizes from the City’s table for louvred concrete soakwells, which have angled openings along the sides.

Diameter x depth Storage volume Roof area served for a single home
900 x 900 mm 0.573 m³ 46.9 m²
1,200 x 1,200 mm 1.357 m³ 111.2 m²
1,500 x 1,200 mm 2.121 m³ 173.8 m²
1,800 x 1,200 mm 3.054 m³ 250.3 m²

For example, a single home with 200 m² of roof needs 2.44 m³ (2,440 litres) of storage under the table’s assumptions. Two 1,200 x 1,200 mm soakwells give 2.714 m³. That example works if the pipe layout sends no more than 111.2 m² of roof runoff to either soakwell.

Identify paving and driveways separately on the plan. The single-home note in the table uses roof area, while the City’s property development specification accounts for runoff from all impervious surfaces. Those are surfaces such as roofs and hard paving that shed water. Confirm how to account for paved runoff in the design for your lot.

Placement and Distances

Allow at least 1.8 m from each soakwell to any building footing and 1.8 m to each property boundary. The City’s table gives the clearance to buildings and boundaries, and Design Specification D12 specifies the clearance from footings.

The City’s soakwell table also says, “Soakwells must be located at the front of the property where possible.” Mark the soakwell’s outside edge, the footings and the lot lines on the site plan to see if the proposed position has enough room.

Approvals and Inspections

The City’s development application checklist calls for a stormwater plan with most planning applications. The City can waive it for minor work. If there’s no existing drainage system, the checklist requires a plan showing where the proposed stormwater system goes and how it disposes of runoff.

For a road-drainage connection covered by D12, the City calls for notice at least 48 hours before drainage work starts and again when it finishes. That gives the City a chance to inspect the work. For on-site soakwells, check the approval conditions before backfilling. If those conditions call for an inspection, arrange it while the installation is still visible.

Local Soil and Exceptions

The City’s soakwell table assumes clean sand and a soakwell base at least 2 m above the groundwater table. When groundwater rises above the base, it takes up part of the storage volume. The City notes that soakwells may be unsuitable in those conditions.

Silty clay absorbs runoff more slowly than sand. The City identifies this issue around greater Midland, Guildford, South Guildford and Hazelmere, where subdivision or development can need extra drainage infrastructure. Use the instructions for the City’s property map to open the Stormwater Management layer and look up your address.

If the lot is listed as “Council connection with silt pit”, the guide to City stormwater connections calls for storage on your property before overflow reaches the road drainage network. The last pit on the property must be a silt pit, which catches sediment before the water reaches the City’s nominated drainage pit. Check the connection point and storage volume for your lot before finalising the drainage plan.

WA Soakwells

Soakwells installed right, with a 10-year warranty