Stormwater Pipe Sizes for Houses in Australia
DN 90 is a common stormwater pipe size for an individual house downpipe run. DN 100 or DN 150 can suit a line that collects more water, if the drainage design calls for it. Choose the pipe size for the area that drains into that run, the local design rainfall and the fall you can achieve on site.
Published Updated
WA Soakwells
Water where it shouldn’t be?
We install channel drains, driveway grates and stormwater pipe, and connect downpipes, so water stops before the house.
No call-out fee
Common Stormwater Pipe Sizes
The common sizes to compare for a house are DN 90, DN 100 and DN 150. DN is the nominal size on the pipe. Use the manufacturer’s outside diameter and fitting series when you connect to an existing pipe.
| Nominal pipe size | Example outside diameter | Where it can be used |
|---|---|---|
| DN 90 | 90 mm | A branch carrying roof water from an individual downpipe to a soakwell or a larger drain. |
| DN 100 | 110 mm (PVC DWV example) | A collector taking roof water from more than one branch, or a driveway drain outlet where the design specifies that size. |
| DN 150 | 160 mm | A main line with a higher design flow, such as one collecting both roof water and runoff from paved areas. |
The dimensions are examples from Australian PVC product tables. A 110 mm measurement across the outside can mean DN 100, so read the pipe stamp before picking a socket or reducer.
Choosing a Size for Your Roof Area
Size each pipe for the roof area that drains into that section. Add the roof sections where their pipes join. If the run also collects driveway runoff, include the flow from that paved area when sizing the common pipe.
Use the design rainfall intensity for the site and the type of drain you’re sizing. The Bureau of Meteorology’s design rainfall data gives intensities for different storm durations and probabilities. Use the duration and probability that apply to your design under AS/NZS 3500.3.
For example, suppose two roof sections each send runoff from 60 m² into the same buried line. At an assumed intensity of 150 mm/h, that combined 120 m² of roof receives about 5 litres per second. Size the shared section for that combined flow in this example. The flow figure alone cannot tell you which diameter will carry it at the available fall.
Go up a size if the calculated flow exceeds what the smaller pipe can carry at the planned grade. Check the larger pipe’s capacity at that grade before buying it. If the outlet sits too high to achieve the minimum fall, changing the pipe size alone will leave the level problem unresolved.
Stormwater and Sewer Grade Pipe
For a standard buried gravity stormwater run, look for PVC stormwater pipe marked AS/NZS 1254 and match the stiffness class to the design. SN is the pipe’s ring stiffness class, which describes its resistance to being squeezed out of shape. For example, Australian manufacturers sell DN 90 stormwater pipe in SN2 and SN4.
Sewer-grade PVC commonly carries the marking AS/NZS 1260 for drain, waste and vent (DWV) pipe. That grade is made for uses such as gravity sewerage. Use a different grade or class on a stormwater run only where the design specifies it. Under a driveway, check the pipe class and the required cover together before choosing the pipe.
Fall for Each Size
The Australian minimum grades in Table 6.3.4 of AS/NZS 3500.3 are the same for these three gravity site drain sizes. A particular drainage design can call for a steeper grade.
| Nominal pipe size | Minimum fall | Drop per metre |
|---|---|---|
| DN 90 | 1:100 | 10 mm |
| DN 100 | 1:100 | 10 mm |
| DN 150 | 1:100 | 10 mm |
The pipe fall calculator converts a grade and run length to the total drop you need. For example, a 12 m run at 1:100 needs 120 mm of drop. Compare that drop with the difference between the inside bottom of the pipe at each end. If the drop available is too small for the design, resolve the route or outlet level before ordering the pipe.
WA Soakwells
Soakwells installed right, with a 10-year warranty
Free quotes and no call-out fee. We size the system to your roof and council rule, install it and back it for 10 years.